

Remediation & Enabling Works - Stephenson Street
Client: Berkeley Homes
Sector: Residential / Infrastructure
Project Overview
Provectus supported the transformation of a former gasworks and railway sidings site into a new residential-led development. With a legacy of hydrocarbons, asbestos, and heavy metals, plus proximity to sensitive Network Rail and London Underground assets, the project demanded a highly controlled remediation and enabling works package.
Key Challenges
-
Hydrocarbon, metals, and asbestos contamination.
-
High risk of unexploded ordnance (UXO) due to historic railway sidings.
-
Live constraints working alongside Network Rail and LUL assets, including high voltage cabling.
-
Temporary works designs required adjacent to Jubilee Line and C2C viaduct.
Our Approach
-
Developed a Materials Management Plan to maximise reuse of site-won soils.
-
Excavated and levelled 56,000 m³ of soils, re-engineered 32,000 m³, and disposed of 9,500 m³ safely off-site.
-
Installed 21,000 m² of 6F2 piling mats for foundation works and pedestrian bridges.
-
Completed UXO clearance using a rig-mounted magnetometer under specialist watching brief.
-
Delivered Category 2 and 3 temporary works designs to protect adjacent rail infrastructure.
-
Worked under HV supervision to safely excavate around Network Rail’s assets.
Project Outcomes
-
Provided a remediated, safe platform for new housing and infrastructure.
-
Ensured full compliance with Network Rail and LUL safety standards.
-
Reduced off-site disposal through targeted reuse strategies.
-
Enabled piling and bridge construction works to proceed without delay.
Key Numbers
-
56,000 m³ cut to construction level
-
32,000 m³ fill reused
-
9,500 m³ soils disposed off-site
-
21,000 m² piling mat installed

