top of page
Stephenson Street 2.png

Remediation & Enabling Works - Stephenson Street

Client: Berkeley Homes
Sector: Residential / Infrastructure

Project Overview

Provectus supported the transformation of a former gasworks and railway sidings site into a new residential-led development. With a legacy of hydrocarbons, asbestos, and heavy metals, plus proximity to sensitive Network Rail and London Underground assets, the project demanded a highly controlled remediation and enabling works package.

Key Challenges

  • Hydrocarbon, metals, and asbestos contamination.

  • High risk of unexploded ordnance (UXO) due to historic railway sidings.

  • Live constraints working alongside Network Rail and LUL assets, including high voltage cabling.

  • Temporary works designs required adjacent to Jubilee Line and C2C viaduct.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Our Approach

  • Developed a Materials Management Plan to maximise reuse of site-won soils.

  • Excavated and levelled 56,000 m³ of soils, re-engineered 32,000 m³, and disposed of 9,500 m³ safely off-site.

  • Installed 21,000 m² of 6F2 piling mats for foundation works and pedestrian bridges.

  • Completed UXO clearance using a rig-mounted magnetometer under specialist watching brief.

  • Delivered Category 2 and 3 temporary works designs to protect adjacent rail infrastructure.

  • Worked under HV supervision to safely excavate around Network Rail’s assets.

 

 

 

 

 

 

Project Outcomes

  • Provided a remediated, safe platform for new housing and infrastructure.

  • Ensured full compliance with Network Rail and LUL safety standards.

  • Reduced off-site disposal through targeted reuse strategies.

  • Enabled piling and bridge construction works to proceed without delay.

Key Numbers

  • 56,000 m³ cut to construction level

  • 32,000 m³ fill reused

  • 9,500 m³ soils disposed off-site

  • 21,000 m² piling mat installed

bottom of page